AnsweredAssumed Answered

Advanced CTF R12 Configuration - Other Cost Pools

Question asked by aburkert on Oct 10, 2018
Latest reply on Oct 12, 2018 by Debbie Hagen

After importing the Cost Center Mapping, I seem to end up with one "Midrange" item and two "Midrange_|_1" items. The latter obviously do not translate to an IT Resource Tower. 

 

I have renamed them and they translate now to the "Compute" resource tower - would this be correct or how should this best be handled?

 

https://internaltraining1.apptio.com/#dataTable:dev%252Fadmin%2540enablement01.com:-@Cenablement01.com%253ADRU_Burkert/D… 