AnsweredAssumed Answered

I'm not getting any numbers on the Budget model

Question asked by Debbie Hagen Employee on Jan 26, 2018
Latest reply on Jan 26, 2018 by Debbie Hagen

Christy Harrod

 

Hi Christy, moving this to Ask an Instructor so I can take a look and maybe others can benefit from how we solve it.  

 

I'm not getting any numbers on the Budget model after I append the Cost Source Planned Transform data to the Cost Source Actuals Transform. There are no dollars in any of the objects and this is also messing with the variance exercise numbers. Please advise.

 

Can you please post a direct link to your project where it's not showing budget $?   I can probably find your project, because I remember you were in my class, but that way, if I happen to be teaching or in meetings and Jenny or Cliff can get to it first, they will know how to access your project. 

 

Thanks,
Deb